Friday, September 02, 2005

Budget cuts delayed New Orleans flood control work

By Andy Sullivan Thu Sep 1, 7:33 PM ET

WASHINGTON (Reuters) - Bush administration funding cuts forced federal engineers to delay improvements on the levees, floodgates and pumping stations that failed to protect New Orleans from Hurricane Katrina's floodwaters, agency documents showed on Thursday.
The former head of the U.S. Army Corps of Engineers, the agency that handles the infrastructure of the nation's waterways, said the damage in New Orleans probably would have been much less extensive had flood-control efforts been fully funded over the years.
Agency officials said on Thursday in a conference call that delayed work was not related to the breakdown in the levee system and Parker told Reuters the funding problems could not be blamed on the Bush administration alone.
Parker said a project dating to 1965 remains unfinished and that any recent projects would not have been in place by the time the hurricane struck even if they had been fully funded.
"If we do stuff now it's not going to have an effect tomorrow," Parker said. "These projects are huge
Tensions over funding for the New Orleans levees emerged more than a year ago when a local official asserted money had been diverted to pay for the
Iraq war. In early 2002, Parker told the U.S. Congress that the war on terrorism required spending cuts elsewhere in government.